How to measure when a software project is complete

estimationmeasurementmetricsproject-management

I have very limited experience in software project management roles, and I was asked this question by another engineer and I was sort of stumped.

How do I measure when a software project is complete?

The part I'm struggling with is the "measure" part. I know there are measurements such as EVM, but they are more focused on overall project performance. For instance, having a low SPI or low CPI can indicate performance/allocation issues, but it doesn't really indicate how complete a project is.

Is there a rule of thumb here to say my project is XX% complete or am I overthinking this?

Best Answer

The project is complete when there isn't anything left to do that the project sponsor is willing to pay for.