I scheduled some tasks in Windows task scheduler. I installed a third party tool called Bmail that added a task that sends email from the task scheduler independently. It can be triggered at a given time. Does any one know how to set this up so that Bmail task sends emails when the original tasks are run? How do I link two different tasks in task scheduler and have one trigger the other?
Windows – Chain trigger in Task Scheduler in Windows
scheduled-taskswindowswindows-task-scheduler
Best Answer
Sorry if this is considered resurection of an old thread. But i wanted answer on this myself and came here first.
You can have them daisy chained. After the first task, schedule the 2nd task to trigger on the event created when the first task completes. It's all explained a bit messy here, https://blogs.msdn.microsoft.com/davethompson/2011/10/25/running-a-scheduled-task-after-another/
If you want even more control, you can do as one of the commentators done in the blog linked above.
I will update this post more when i've got it to work myself.